UPS CCTV Application

UPS Install

Our client runs a campus environment and has been suffering from regular outages on his CCTV equipment. Throughout the campus the CCTV cameras get their power directly from the street lights. This meant that a UPS solution would not have to power just the CCTV, but the lights as well.

Another problem is that space is a real issue. A competitor had visited this site and had proposed a UPS solution that would fit in a pre-fabricated cabinet outside the comms room, and this would keep the system up and running for a good 12 hours or so. Hmm, this seemed real overkill and a more cost effective solution would be to fit a small UPS within the comms cabinet and use a generator outside. This was a better solution, but not what the client wanted to pursue. Discussing this with the client it became apparent that having the system up and running for 12 hours was more of a wish list than a real requirement. In fact about an hour to 90 minutes would be acceptable. What else can we do?

The site has the street lights split into three zones, each powered from a single phase. This necessitated the use of a three phase UPS System, although the entire power consumption was in the region of 3000W or so. Our standard 10KVA 3phase UPS, the VFI33-10KT would provide around 20 minutes runtime. Not long enough.

Fitting a battery pack comprising a +/-120V strings with 36Ah capacity did the job exactly with a calculated 102 mins of runtime. There’s the solution, now where’s it going to go?

The comms room was a bit of a squeeze. And calling it a comms room is also a bit misleading. It was more of an out-house than anything. The UPS could possibly fit, but then getting in would be a challenge. As luck would have it another outhouse was nearby that we could wire the UPS to. Bring on the electricians.

UPS CCTV Application

A schematic was made up, discussed with the site electrician and a plan put in place to minimise downtime. Phase 1, the electrician would run cables to the outhouse and fit the UPS input and output breaker panels. Phase 2, UPS installation, leaving it in bypass mode. Phase 3 involved unavoidable downtime where the power feeds to the cameras needed to be diverted to the UPS.

Once this was completed, the UPS internal bypass made sure that power was still being presented to the CCTV. All that was left was for Power Inspired to come back to site and commission the UPS System. Take it out of bypass and switch it online. All completed without any downtime.

Happy days, over 90minutes autonomy for a CCTV UPS application from a 10KVA 3phase UPS System with additional battery cab.

Posted on Leave a comment

Case Study: 2.3KW 8 hour UPS Solution

Brief:

We were asked by a customers to come up with a UPS solution that will provide 8 hours of runtime for a load of 2300W to provide power for essential services at a new construction project in the Midlands.

Construction Site

The requirement was to deliver, position, install and commission the system and as requested we handled the project from Concept through to the Execution.

The first part is to ensure we have a UPS powerful enough for the load and make the decision on extra battery cabs or a bespoke battery solution. We could use one of our VFI3000T units, a 2700W unit – so powerful enough – and fit extra cabinets to this. The problem is we would need 19 additional cabinets to hit this amount of runtime! Clearly another solution was needed.

Our B16 cabinets (BCAB-B16) are very flexible and can support up to sixteen 100Ah blocks. Looking at the UPS requirement the best solution would be the VFI3000BL. This is a extended run UPS system, meaning it does not contain internal batteries but has a larger charger for connection to a large external cabinet. Most UPS only have a charger rated at around 1A, so connecting a 100Ah battery string would then require around a week to recharge following an outage, with the possibility that the battery would never get to 100% charge. The VFI3000BL has a massive 12A charger so will not suffer from such consequences.

The UPS has an input battery voltage of 72V, which is 6 blocks in the battery string. We can fit 2 strings in the B16 cabinet and this would give us a 72V 200Ah battery. Even with this capacity the runtime was still too short at only 4 hours. A second B16 cabinet would do the trick. With a further two strings added the achievable runtime was now calculated to be 9 hours and 48 minutes. Not only does this provide some overhead in the 8 hours requirement, it extends the working life of the installation as the batteries degrade with time and so 8 hours will still be achievable years from now. As longevity is an issue, the batteries used were our 100Ah deep cycle blocks, with 10 year design life (6FM100E-X). Not only that, but these blocks are rated at 100Ah when discharged at 10% of capacity, rather than lower cost blocks which are rated the same but at a 5% of capacity discharge (this is 10hour vs 20hour rating for those who know about such things).

So now the design of the system was finalised we had to plan the install on site.

Installation:

First thing was to get our Wall mounted Maintenance Bypass Switch installed on site. This was sent to site in advance for the site electricians to install. This would allow ongoing power to be connected to their systems if they so desired and we can connect the UPS into play without affecting ongoing operations should this be required. 

The B16 cabinet comes as a flat pack assembly which delighted the client. Previously for another site he had a battery cabinet delivered that weighed over a ton and had to somehow get this maneuvered into place. Not only did this prove to be extremely difficult, but the physical toll of this caused injuries to some personnel. In our case the two B16 cabinets and 24 batteries came on a pallet in the back of the company van and these were fork lifted off and placed just inside the building. We then decanted the pallet in manageable loads onto a trolley and wheeled these into position.

Battery cabinet install b16 cabinet

Note the finished B16 cabinet on the right, the second cab under construction and the wall mount bypass switch.

As usual, something unexpected does crop up and we try to plan for the unexpected. The client’s preferred position for the cabs was in the centre of the room but some ducts that was supposed be on the far left happened to be placed directly under where the cabs were supposed to be. However the footprint of the cabs and the UPS is so small we were able to put the cabs adjacent to the ducting and in a more preferred location. Once this was decided the first cab was assembled, followed shortly afterward by the second cabinet. For safety reasons we only have one person making connections to the cab at any one time. Here our qualified technician Ray (complete with ECS approval) did a sterling job.

Each cab is fitted with a DC breaker / isolator and the configuration is such that individual strings or the cabinets can be isolated to allow for relocation or service, not only maintaining power to the system (as you would with a bypass), but also maintaining UPS support.

Once the cab was assembled and tested, the UPS was connected and configured as per the clients requests. Positioning of the UPS is important to ensure adequate air flow and ease of operation and it was decided to be placed behind the cabinets in vertical orientation. This allows all cables to be neatly out of the way whilst allowing ease of viewing of UPS status. However this site was still a building site and so the floor was not yet finished and there was excessive dust that would be sucked into the UPS causing problems down the line. As a result the leads connecting to the UPS were made long enough for the UPS to sit in horizontal orientation on top of the B16 cabinet whilst work was completed and to be moved into position at a later date.

Finished project:

Install complete - b16 cabinet

Once we’ve confirmed correct operation all was done and the client was then ready to connect his data cabinet up complete with UPS support.

Not only did Power Inspired provide a technically sound electrical solution, the physical properties were also a bonus to the customer, coupled with an ease of installation and a job that was completed in well under a day – including the all important ‘site inductions’.

A successful Project delivered with top-rate communications from our customer. Thank You R.